Project report 2

Tritin Truong edited this page Feb 19, 2019 · 15 revisions

Introduction


Meeting Minutes

Sprint retrospective:

Date: February 19 2019
Time: 11:30 AM

In attendance:

  • Zirui He
  • Binyuan Sun
  • Tritin Truong
  • Zhong Yu Yang
  • Mark Zhu

Retrospective
Team discussion about problems with the previous sprint, team looked over the feedback for the previous sprint. Technical problems were as follows:

  • Requirements model were not specific enough
  • Use case diagrams were missing names and were too large
  • UML model: some classes were missing and missing association classes
  • Testing of the persistence layer was missing documentation
  • Testing did not check for attribute or reference persistence
  • Code style, names were too short
  • Lack of documentation for running the tests

Appropriate problems will be addressed as issues in the following sprint.

There were also issues with time management, the project was started approximately a week before the deadline, and as such we were strapped for time near the end of the sprint. Teams will start working at a much higher frequency to compensate.

Task Distribution

Team looked over project requirements and discussed time frames and feasibility. Discussion about

Task were distributed as follows:
It was decided that every member shall work on a use case, which includes implementing the business method, writing the unit test and contributing to the Quality assurance document.

Next meeting
Meeting was adjourned, members were tasked with reading up on their use cases and starting the implementation